PROGRESS CRIT 2
DATE : 6 NOVEMBER 2015
TIME : 10.00 A.M.
VENUE : GROUP 4 STUDIO RUS104, SCHOOL OF HBP, UNIVERSITI SAINS MALAYSIA
LECTURER:
- ASSOC. PROF. DR. FUZIAH IBRAHIM
- DR. SITI SALWA MOHD ISHAK
- DR. MARIATI TAIB
PRESENCE:
- AZIMAN RAZIQ BIN RIZAMAN (CHAIRMAN)
- AIMI ZAHIRAH BINTI ZULKARNAIN (ASSIST. CHAIRMAN)
- NOR SYAFQAH ATHIRAH BINTI MOHD SHAIFULLAH (SECRETARY)
- WEE CHEW TENG (ASSIST. SECRETARY)
- TAN JO YEN (TREASURES)
- LEE TER SOON
- NG YII ROU
- AZREEN SABRINA BINTI AB HALIM
- FAIZ SOLEHIN BIN SHAFIKHULLAH
- FATIN NABILA BINTI ABDULL RAHMAN
- GOH SU CHEN
- HANISAH BINTI AMIRUDDIN
- NUR NABILAH BINTI MOHAMAD BAKHTIAR
- MUHAMMAD HAKEEM BIN MOHD MAHAYUDDEEN
- GOH JIE XIN
- NUR SYAHIRAH BINTI ALI
- NURMAN BIN RAZALI
Chairman Remark
The chairman begins the meeting with
salam remarks and welcome to the members who present in the meeting.
Minute 1: Prepare for
the Crit Session
·
All member of Group 4A&4B are
prepare the A1 butter papers with all the information to fill on the partition
board.
Action: All
member of 4A&4B
Minute 2: Welcoming from the lectures
·
Lectureres begin the session with some
advice for all the member. We are having this crit session together with group
4A.
Action:
Lecturer
Minute 3: Presentation of group 4A
·
The
member of the group 4A stand out to present their work. For this crit session, the
group is presented by the site analysis and some sketches of the design
concept. They also propose SWOT analysis, key plan, site plan location plan,
section drawing for the ground, elevation of the ground, humidity, temperature,
sun path, wind flows and facilities & street furniture of site no. 7.
Besides, architecture and Planning from group 4A were produced sketches of the
draft design concept and the site planning. Lectures give comments from time to
time as presentation goes on.
Action:
Member of group 4A
Minute 3: Presentation of group 4B
·
Group 4B stand out and started to
present in front of lectures and group members. Our chairman took the first
step to greet the lecturers and other member are present what we had done
before.
·
The items that presented by group
member were:
a) Key plan and location plan (NTS)
b)
site analysis ( Services, facilities, temperature, wind. humidity, luminance,
c) SWOT analysis
d) Site plan (sun path, wind flows,
pedestrian pathway etc)
e) Precedent studies (Sultan Azlan Shah, sports)
f) Concept of the design (hockey ball, bubbles ,dome)
g) Sketching of the design
h) Bubbles diagram and site planning
g) Gantt Chart ( progress scheduling )
·
Lectures
give comments from time to time as presentation goes on.
Action
: All member
Minute 4: Comment from of studio
master.
After our group finished our presentation,
lecturers gave their comment and feedback about what aspects should be
improved. The feedback and suggestion that lecturers gave to group 4B
were :
·
the data and
information of site analysis and SWOT analysis is clear and improved.
·
Lack of research about
the precedent studies of design
·
The idea of design
must come from precedent studies
·
Lack of relationship between the precedent
studies and the pavilion
·
The design of the pavilion do not
have overhang that can avoid the direct sunlight into the structure.
·
The
location of the pavilion is too near with the lake (dangerous).
Action : All lecturer
Minute 5:
Discussion for the Crit Session and Discussion and update the design of the pavilion
After the Crit Session 2, all the member is discussion for the precedent
studies and modify the problem. First, we need to change our precedent studies then only can come out the idea of design from the precedent studies. Second, the
design of pavilion that we need to add on the overhang for pavilion to avoid the direct sunlight into the
structure. After the discussion , we decide to add on extended louvers for sun shading and decoration for the
pavilion. For the material of this pavilion, we also do some changing
and we build it with the reinforced concrete lower beam, reinforced concrete
post, rectangle glass panels (LTG),Laminated tempered glass, recycled steel
frame-work and photovoltaic cell.Aimi Zahirah ( Architecture student ) is sketching the new pavilion and show it to all the member after discussion .Every member from Group 4B is acceptable, architecture student can proceed to floor plan, elevation, horizontal and longitudinal section during the holiday.
Action: All member
Figure 7: New sketches for design of the pavilion (Update).
Meeting 6: Distribution
the work for next Presentation Crit session (Planning of work)
Chairman and construction management student are distribution the work
for member. So, the member can do their work during the mid-sem break (week 3).
Chairman is give instruction to the member. The design and planning team need
to modify the design to solve those problem. So, we only can proceed to Floor
plan, Elevation, Horizontal and Longitudinal section. For the non-design team,
they need to study about construction report, material selection, building
services, elemental cost analysis. They need to research information for own task and do a simple
draft for next meeting that will more fast for us to proceed. For the construction
management student must complete and update the meeting during the holiday.
Action : Chairman
Nor
Syafiqah Athirah Binti Mohd Shaifulah
Wee Chew Teng
The chairman closes the meeting with
remarks of thank you to the members who attend and the next meeting
will be held on Sunday (15/11),
8.00pm.