Meeting Report
MINUTE
OF MEETING GROUP 4B SITE NO.8
Date:
15 November 2015 (Sunday)
Time: 8.00 pm-12.00
Venue:
DUP,USM
_____________________________________________________
Presence:
- Aziman Raziq Bin Rizaman ( Chairman )
- Aimi Zahirah Binti Zulkarnain (Assist. Chairman)
- Nor Syafiqah Athirah Binti Mohd Shaifulah (Secretary)
- Wee Chew Teng (Assist.Secretary)
- Tan Jo yen (Treasures)
- Lee Ter Soon
- Ng Yii Rou
- Azreen Sabrina Binti Ab Halim
- Faiz Solehin Bin Shafikhullah
- Fatin Nabila Binti Abdull Rahman
- Goh Su Chen
- Hanisah Binti Amiruddin
- Nur Nabilah Binti Mohamad Bakhtiar
- Muhammas Hakeen Bin Mohd Mahayuddeen
- Nur Syahirah Binti Ali
- Nurman Bin Razali
- Goh Jie Xin
Chairman Remark
The chairman begins the meeting with salam remarks and
welcome to the members who present in the meeting.
Minute
1 : The new precedent studies ( Updated )
Due to the problem of the original precedent studies from
the crit session, Aimi is present two precedent to all member about our new precedent
studies.
The
1st precedent studies is come from Rising Moon Pavilion(Hong Kong).
This is temporary pavilion for 2013 Hong
Kong Mid-Autumn Festival. As a temporary
pavilion, the designers using thousands of polycarbonate plastic bottles that were recycled after deconstruction. This pavilion is
sits on reflection pools so having a complete sphere when reflects. Each water
bottle was connected with a Light Emitting Diode (LED),so is low energy
consumption.
The 2nd precedent studies is come from Reichstag
Dome(Germany).
A glass dome Reichstag
Building, Berlin by architecture Norman Foster. Symbolizes the reunification of
Germany. It is open public and also can be reached by climbing two steel
spiraling ramps. Steel and rectangular glass panels.
Action:
Aimi Zahirah Binti Zulkarnain
Minute
2: Design Proposal (Floor plan,
Elevation, Horizontal and Longitudinal section)
According to the feedback from the lecturer about the
design of pavilion, the architecture student are modify the design of the
pavilion.The different between the previous design with new design is we
already add on the extended louver for sun shading and decoration ( slanted 10-50
)- 500mm and the material for the extended louver is using PU. Architecture student also add on a small courtyard inside the pavilion that connected with the open roof For the other
material of this pavilion, we also do some changing and we build it with the
reinforced concrete lower beam, reinforced concrete post, rectangle glass
panels (LTG), laminated tempered glass (rectangular glass plane of different
sizes according to levels), recycled steel frame-work and photovoltaic cell.
Then, the area of the pavilion is estimated that is landscape= 10.7m2 ,
gallery= 25.0 m2, lounge+ reception= 22.5m2, store=
2.5m2, porch= 3.3m2, total building area= 50.0m2
and total building line area= 64.0m2. Architecture student also draw
the floor plan, elevation, horizontal and longitudinal section of the pavilion.
Figure 8: Design Proposal (Floor plan, Elevation, Horizontal and Longitudinal section)
Action: Aimi Zahirah
Binti Zulkarnain
Minute
3: Preparation for the Presentation Crit 1
All the member are transfer the information into the A1
butter paper according to the job scope. For the building technology student is
do the construction method report. For this pavilion we use the Industry
Building Index (IBS) method. IBS is a modern method construction. It can
increase productivity and quantity at construction site and allow more
efficient and cost effective. For the proposed foundation( material selection team) ,raft foundation
suitable because low bearing capacity soil. The soil settle unevenly when subjected
to load. For the glass of the pavilion, we use laminated glass because PVB
interlayer keeps the layers of glass bonded & prevent from cracking apart.
Construction management student is do the project scheduling and organisation
chart. After that, all the member is combine and arrange all the A1 butter
paper.
Action : All member
The chairman closes the meeting with
remarks of thank you to the members who attend.